Automation Portals
- Automatic Identification
- Design & Simulation
- Digital Factory
- Electrical & Control Panels
- Embedded Automation
- Factory Automation
- Fieldbus Networks
- Flow, Level & Process Inst.
- Fluid Power, Valves & Pumps
- HMI & Operator Interfaces
- Industrial Communications
- Industrial Computers
- Industrial I/O
- Machine Control
- Machine Safety
- Manufacturing Intelligence
- Motion Control
- OPC
- Plant Management & Maint.
- PLCopen
- Process Control
- Process Safety
- Programmable Controllers
- Robots & Robot Controllers
- SCADA & RTU
- Security
- Sensors
- Systems Integration
- Test, Measurement & LIMS
- Vision
- Wireless Connectivity
- Network Portals
- EtherCAT
- EtherNet/IP
- PROFINET
- Industry Portals
- Building Automation
- Chemical
- Food & Beverage
- Machine Tools, CNC & DNC
- Material Handling
- Oil & Gas
- Packaging
- Pharmaceutical
- Power & Energy
- Transportation (Microsite)
- Water & Wastewater
- Event Portals
- Hannover Messe
- Industrial Automation NA
- ISA Automation Week
Can't Justify Full Automation? Semi-Automate With Paced Assembly and Robotic Work Cells
The rule of thumb for manufacturers today is that annual sales volume must exceed 1 million before a given product can be cost justified for full automation. The initial investment and payback periods are high when total automation is the goal.
Semi-automation is a cost-effective alternative. The equipment ingredients of such a system are:
-
Synchronous platform conveyor
-
Vibratory part feed system
-
Robotics
Semi-automation addresses a segment of a given product for automation and creates special work cells to accomplish same. It combines the disciplines of materials handling, product mechanization and direct labor control systems. Labor gains of 75% are possible using this method of assembly.
The typical consulting activity sequence necessary to convert products from a bench method of assembly to a semi-automated system is:
-
Phase OneIndexing Paced Conveyor System
-
Work measurement
-
Line balance
-
Final equipment specifications
-
Work station layout
-
Training
-
Paced system installation
-
-
Phase TwoSemi-Automated Work Cells
-
Design and fabrication
-
Programming
-
Electrical and mechanical installation
-
The time-balanced Phase One system prepares for Phase Two semi-automation by eliminating future time bottlenecks for operations not to be mechanized. Phase One gains include:
Improvement Comparison
|
From Bench or |
To Paced Assembly Line |
Labor Gain |
|
|
|
|
|
Handling: |
|
5% - 10% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Methods: |
|
5% - 10% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Performance: |
|
15% - 20% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Average Improvement |
|
25% - 40% |
Phase Two gains in product mechanization leads to additional savings. They include:
|
From Bench or |
To Semi-Automated Cells |
Labor Gains |
|
|
|
|
|
Work Cell Sub Assembly |
|
25-30% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Work Cell S/A to |
|
5% |
|
|
|
|
|
|
|
|
|
|
|
Total Average Improvement |
|
30% - 35% |
|
|
|
|
The initial investment in the semi-automation technique is modest and a first-year return-on-investment guaranteed.
This article is provided by JD Gray Associates, manufacturing productivity consultants specializing in materials handling, product automation and direct labor control systems. Industrial Engineering is the essence of the 25 year old company. For more information, please visit www.jdgray-associates.com.