The following discussion is part of an ongoing column called Ask the Automation Pros, authored by Greg McMillan, 2010 ISA Life Achievement Award recipient, industry consultant and author of numerous process control books and articles. Submit your questions to [email protected] with “Ask the Automation Pros” in the subject line. Browse previous questions and answers here. Past Q&A videos are also available on the ISA YouTube channel; you can view the playlist here.
Erik Cornelsen’s Question
I’ve been working on a challenging commissioning project over the past few months and would be interested in gathering insights from the Automation Pros community on best practices, lessons learned, and tips for successful commissioning. In particular, please address topics such as sign-offs, team responsibilities, documentation, interlocking, and sequencing testing.
Michael Taube’s Response
Three factors determine the successful (no surprises) commissioning of a plant and/or control system (in fact, I did a joint presentation on this very subject last month at the Texas A&M Instrumentation & Automation Symposium):
- Documentation,
- Documentation,
- Documentation.
All hyperbole aside, the necessity of usable documentation can’t be overstated. So much of what passes for documentation these days is comparable to “quality plans” that no one (except auditors) will ever read. Therefore, the documentation that is created for the project must be designed for everyday use by operations, maintenance, and engineering after the plant is commissioned and turned over to the client. In terms of functional checkouts, documentation should be thoroughly tested during factory acceptance testing (FAT). Complex applications (i.e., safety instrumented systems (SISs), sequence controls, interlocks, etc.) require more detailed documentation and testing before going to the site; if these tasks are not completed, you’re setting yourself up for a lot of trouble on site.
FAT documentation can vary based on the nature of the loops: simple indicators and control loops should have a minimum of instrument range and engineering units, input characterization (linear, square root, etc.), loop description, alarm limits and priorities, and control action and preliminary tuning constants (where applicable). “Complex” applications require more exposition, usually as a control narrative document, cause and effect diagram, or in another form. Format and information content can vary depending on the nature of the application, but (again, under the auspices of “usable”) they should be written for use by the client once care, custody, and control of the plant is turned over to them.
Team composition, while ostensibly the same regardless of project size or complexity, should be appropriate to the scope; team size is also based on the overall scope and scale of the project (i.e., a larger scope requires more and/or larger teams). Typically, engineering and operations are the main groups from the client, but instrumentation and electrical (I&E) maintenance should be involved during, if not before, FAT: after all, they will be responsible for post-commissioning maintenance, so they should have some say in the design.
As should be evident, FAT is the singularly most important aspect of any automation system project: everything is visually and functionally confirmed to conform to the client’s requirements. The format of the acceptance documentation can vary depending on the overall scope and scale of the project, but the operative phrase should be “keep it simple.” I’ve seen some projects classify document “quality” based on the weight of the paper used to print it. (Lawyers must’ve been involved in their creation.)
At a site, the most significant factor I’ve noticed that affects smooth commissioning is the folder organization for loops: there is one for every indicator loop and one for every control loop. At a minimum, these folders should include the following:
- Piping and instrumentation drawings (P&IDs) with the subject instruments highlighted
- Instrument location diagrams with the instruments highlighted
- Calibration procedures and installation standards for the measuring instruments and, where applicable, the final control elements
- One or more sheets that replicate the information contained in the FAT document (perhaps the original acceptance document)
- A loop diagram that shows every connection from the field to the control room and from the control room to the field (where applicable), including JBox and marshalling terminations, cable IDs, and so on
A sign-off sheet indicating results of scale testing (i.e., 25%, 50%, 75%, and 100%)
These loop folders can then provide the basis for ongoing maintenance records. While there is an obscene fascination with electronic files and documentation these days, good old-fashioned hard copy is far easier for a technician to grab at a 3:00 a.m. or weekend call-out.
Sigifredo Nino’s Response
Building on Michael’s contribution, here is what that weekend call-out looks like without a loop folder. Shortly after I moved into pulp and paper as an instrumentation and control engineer, I was on a weekend shift supporting the integrated pulp plant and paper machines when the newly commissioned paper machine shut down. I was called in, and four hours later we traced the problem to a defective limit switch. When I was asked why it took so long, I answered that there was no documentation whatsoever on either the programmable logic controller (PLC) program or the equipment.
I later learned that the instrumentation and controls (I&C) engineer in charge of the project had been asked to cut costs, and documentation appeared to be too expensive. As I have seen before, what was supposed to be a saving in capital expenditure (CapEx) became a cost to operational expenditure (OpEx). A contract was eventually awarded to a consulting company to produce the documentation that should have come with the project.
Hunter Vegas’s Response
As a veteran of countless commissioning teams, I can offer a few ideas that have proven to be very useful on large project commissioning efforts:
- I totally agree that accurate loops are a must. Nonexistent or inaccurate loops will create a nightmare.
- If the project is a retrofit or has significant existing instruments scattered across multiple floors of a large facility, we have knowledgeable instrument technicians put large red tags on each instrument with the tag number written on them well in advance of the outage. That helps outside instrument technicians find them quickly during commissioning. (We also put a rough location on the loop sheet, so they know where to start looking.)
- One thing I created years ago was a one-page, simple checklist for all major instruments that we included with the checkout package. It listed 8 or 10 things that you needed to check on each instrument type. For instance:
- Vortex meter: Flow arrow, right? Meter run acceptable? Centering rings installed, seal-off present? Union on seal-off?
- Orifice: Tubing traced? Tubing sloped correctly? DP H/L, correct? Meter run? Tubing tight? Tags on devices?
Originally, the list was for me because I was new and might forget something. Later I found out that everyone was using it because it ensured a complete and consistent loop check and served as a commissioning document. Here are a few additional best practices that we implemented:
- To keep things moving, we assigned a dedicated “troubleshooting” team(s?) on each shift consisting of very knowledgeable technicians and/or engineers who would only chase down and resolve problems. If a normal checkout team ran into an issue, they just flagged it and moved on to the next loop rather than spending hours spinning their wheels. This kept the commissioning moving, and the dedicated troubleshooting team could often find/resolve the problem in just a few minutes.
- Commissioning is a good time to get the control room operators involved so they can learn the system. However, I always have a knowledgeable engineer in the room beside them who can quickly bypass interlocks and/or answer questions, so they don’t slow the process. A knowledgeable control room operator and/or engineer can field and keep ahead of at most three field teams. (More than that slows things down too much, and the field guys get frustrated waiting on others.)
- My engineer in the control room has a copy of the tag list spreadsheet on a computer and notes as loops are checked off or documents issues as they are found and/or resolved. A simple spreadsheet calculation provides an instantly updated percentage-complete figure that plant managers are forever demanding.
- Furnish free coffee in the checkout trailer. Other trades will stop by to use it, and you can find out exactly how the commissioning efforts are going across the yard well in advance of the “official status” provided in the shift change meetings.
Lucinda Weaver’s Response
Having started numerous facilities in a validated pharma environment, I am going to agree with all of the above and add a little more.
Start early—while construction is still ongoing. The easiest commissioning projects I ever had started with what we called the quality assurance (QA) mechanics: two people, a senior site pipefitter and a senior site instrument mechanic, who went out on the project with P&IDs and wiring drawings, following up with the construction as it was ongoing. They checked the proper placement of the instruments in the line, not just for flow arrows and tags, but also to determine whether the maintenance person could reach the instrument to do their job later. The instrument person checked all the wire numbers, terminations, panel markings, locations, and many other things. Their master set of highlighted and red-lined drawings was the first part of the validation package. When the loop check was actually performed, the same instrument mechanic would be the field person (or one of them; I could easily sit on the console and drive two or three field teams) to go to each instrument and either force the signal into the system or watch the device when I did an output from the system. At this point, I had the instrument commissioning sheets derived from the instrument database to complete with the results of both the as-found and as-left for all the devices.
Note: The software in the control system needs to be at least as far through the FAT as to check that the correct input and output show properly on the primary graphic. Loop check is the check of the full loop: outputs driven from the console and the correct response inputs from the field. Simply driving an output or input as far as the input/output (I/O) panel is not good enough.
After completing these steps, plus the detailed software FAT with all the sequences and failures tested, the next step of your commissioning, your “water batching” (or whatever you use to do the testing), is usually pretty easy.
Greg McMillan’s Response
Lucinda Weaver provided extensive details and guidance in the following Control Talk columns on how to achieve the best documentation for automation projects that is essential not only for design but for commissioning, maintenance, and continuous improvement.
- September 2026 Control Talk: “Achieving effective instrument specifications”
- October 2026 Control Talk: “Past and present instrument index”
Lucinda also provided knowledge on how to best deal with packaged equipment in the following Control Talk Column.
- November 2026 Control Talk: “Packaged equipment pitfalls: What instrument engineers must demand before the 2 a.m. breakdown”
I have experienced many situations where the packaged equipment supplier is using the cheapest automation system. You must be involved from the beginning and ensure that the supplier uses the transmitters and control valves that you have determined to be best for interfacing with your automation system controllers. I recommend doing FAT before it is shipped.
I have seen so many control valve, variable-frequency drive (VFD), measurement, configuration, and tuning problems that can mess up commissioning systems. I advocate knowing the watch-outs and rules of thumb at the end of each tip in 101 Tips for a Successful Automation Career (ISA) and the best practices at the end of each subsection in the Process/Industrial Instruments and Control Handbook, Sixth Edition (McGraw Hill), and paying particular attention to:
- Ensuring on-off valves with a high capacity, low leakage rate, and low cost, posing as throttling valves, are not used. Make sure the valve resolution is better than 0.5% and lost motion is less than 0.5%, with a nearly linear installed flow characteristic by using the knowledge in ANSI/ISA-TR75.25.02 and specifically Annex A - “Valve Response and Control Loop Performance - Sources, Consequences, Fixes, and Specifications.”
- Using cascade control of speed-to-torque in the VFD with a generous amount of torque, high-resolution input cards, minimum rate limiting, and an inverter-duty motor.
- Making sure impulse lines will not introduce errors in differential pressure and pressure measurements by the accumulation or disappearance of fluids in impulse lines.
- Using minimum damping in pressure transmitters and signal filter settings in controllers.
- Using middle signal selection of 3 pH electrodes that have been acclimated to the solution and installed in process lines, preferably vessel recirculation lines, when process fluid is flowing.
- Using sheathed, spring-loaded sensors in tapered thermowells with head-mounted or nearby installed transmitters to minimize sensor wiring.
- Using high-fidelity, dynamic simulations with a digital twin to test the configuration, strategies, and proportional-integral-derivative (PID) tuning and getting operations, design, and maintenance on the same page by providing training sessions and the ability to explore and learn using a digital twin.
- Ensuring that the controller execution-rate-time interval is less than 20% of total loop dead time.
Commissioning, system performance, and safety could be much better if documentation included the accuracy and rangeability of measurements and the resolution, lost motion, and rangeability of control valves that take into account the installation and process conditions. Note that the lowest controllable flow in valve rangeability is set by the resolution and lost motion near the closed position of the installed flow characteristic, whereas the literature often says the lowest flow is where there is a specified deviation of actual valve flow characteristic seen in installation from the theoretical inherent flow that is characteristic in the literature.
Peter Morgan’s Response
The successful commissioning of an automation system is almost entirely dependent on preparation. Unfortunately, activities that might be described as “preparation” are often undervalued and the target of cost-cutting measures and/or measures to advance commissioning. It should be understood that not being properly prepared for commissioning can lead to delays in commissioning or operating losses, and in extreme cases, a cascading outage and equipment damage.
Below is a list of the resources and activities that, for me, have proven to be the “gold standard” for success in commissioning.
Control narrative
The control narrative is the reference for the design of the control systems, a resource for control system testing and commissioning, and a permanent record of the intended functionality of the control system.
The control narrative describes the process control philosophy, and for each loop, special provisions to aid start-up, interlocks, alarms, overrides, discrete control, and interfaces to specialty control systems.
The control narrative and functional logic diagrams should be used as reference documents for the tests, and they, together with the procedure and recorded results, form the record of compliance with the design intent.
Loop diagrams and alarm lists
Loop diagrams document I/O for regulatory and discrete control, and inputs (analog and discrete) for indication and alarm. The alarm lists serve to record the process alarms and should include physical input references, controller internal references, and display references.
Functional logic diagrams (e.g., SAMA-type diagrams)
Functional logic diagrams should form the reference document for the design, configuration, and testing of the control system, and serve as the resource describing the intended functionality of the control system. While control system configuration is typically self-documenting and function block status can be viewed in real time during testing (an asset for troubleshooting), the functional logic diagram, as the acknowledged record of intent, provides the reference for testing and a means to record acceptance.
Factory acceptance test procedure
Essential to the execution of the FAT is a detailed written procedure with expected behavior described. The control narrative and functional logic diagrams should be used as reference documents for the tests, and they, together with the procedure and recorded results, form the record of compliance with the design intent.
When implementing (configuring) complex control strategies, errors that will affect behavior can occur in the selection of configurable options at the function block level. If not discovered during testing, issues with controller initialization (e.g., in ganged or split range control and timing issues in Boolean logic, to name just a few) can be a challenge to resolve during commissioning and can add to commissioning cost or even delays in productive operation. Functional testing also provides the opportunity to verify the design of the operator interface and, with the participation of a control room operator, can provide the opportunity for refinement and early acceptance of the interface.
FAT can be made less onerous and more efficient by configuring very simple feedback models using function blocks that are available for implementing applications. For example, in a motor control application, the motor control center (MCC) can be simulated with temporary logic to function as a latch, allowing the display, command fail, and trips to be readily tested without the need to monitor momentary commands and jumper inputs simultaneously, which can be a challenge.
The FAT procedure should include a method for testing every I/O channel and verifying the engineering unit range and that values are properly presented at the human-machine interface (HMI). The loop diagrams and alarm lists serve as the reference for these tests and a record of progress during the tests.
Factory acceptance testing
The FAT is usually (and best) carried out at the system integrator’s facility where a wide range of resources are available. If circumstances dictate that the tests be carried out at the plant site, risks should be assessed and mitigating actions put in place to minimize risk to persons and operations.
The FAT should follow the test procedure, and any exceptions to the intended behavior should be recorded and resolved. Any revision to the logic, either to resolve issues or improve functionality, should be incorporated in the control narrative and functional logic diagrams. Marking up the functional logic diagrams and test procedure is a good way to track the progress of the tests and record the successful test completion.
Site acceptance testing
The site acceptance test verifies that the functionality verified in the FAT is preserved in the on-site installation and provides the opportunity to test the I/O if not already tested at the FAT. The site acceptance tests should follow the procedure developed for the FAT and, with the engagement of panel operators, can provide an opportunity for refinement and early acceptance of the operator interface.
Pat Dixon’s Response
In industrial projects, I have experienced detailed and focused management of mechanical, electrical, and construction scope, while automation is an afterthought. In one case, I begged for months for details on an alarm configuration, which I did not get until we were performing I/O tests. Bad alarm configuration is why ISA 18.2 was created. Any project that includes automation must include this scope at the start. If this responsibility is entirely within the manufacturer, appropriate attention may not be given to the automation scope. The magnitude of investment in concrete and steel can dwarf automation, yet automation will be critical on start-up. It will be very expensive when there are delays or failures in start-up, and the automation people are blamed for management oversights. At the risk of being zealously commercial, I have seen good results when an independent project manager focused on the automation scope is on the team. Getting the design, testing, and commissioning steps on the Gantt chart and having someone focused on managing that scope can ensure the priorities are proper and start-up surprises are mitigated.